Thursday, June 24, 2010

PR25-06-10 : Progress Report from 19 to 25 June 2010

Laying of rebars








Slab casting


Dry wall setting out







Delivery & fabrication of steel works on site














Thursday, June 17, 2010


installing of BRC started on 17/6/10





lean concrete on 16-06-10

soil treatment and damp proof on 16-06-10