Thursday, October 28, 2010
PR29-10-10. Progress Report from 23 to 29 Oct 2010
Casting of future Main Entrance
Construction of brick wall at Receiving Pavilion
Drainage outside swimming pool area
Laying of main cable by PUB
Friday, October 22, 2010
PR22-10-10. Progress Report from 16 to 22 Oct 2010
Sanitary for Public powder
Construction of bench at Receiving Pavilion
Construction of drainage in progress
Thursday, October 14, 2010
PR15-10-10. Progress Report from 9 to 15 Oct 2010
External wall finish & painting works
Floor screed at Sales Gallery
Cabinetry works at Office area
Drainage works in progress
Steel works for cover walk-way
Steel works for Receiving Pavilion
Works for retaining wall in progress along future Main Entrance
Thursday, October 7, 2010
PR08-10-10. Progress Report from 2 to 8 Oct 2010
Water-proofing & floor screeding works at Sales Gallery
Steel works for Canopy
Sample for I.D
Glazing for aluminium works
Steel frame for Cover linkway
Structural works for retaining wall at boundary
Friday, October 1, 2010
PR01-10-10. Progress Report from 25 Sept to 1 Oct 2010
Painting works
Installation of compressor
Aluminium frame works for glass door
Steel works for canopy
Cover walk-way base works
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)
Followers
Blog Archive
►
2011
(43)
►
October
(4)
►
September
(5)
►
August
(4)
►
July
(4)
►
June
(5)
►
May
(4)
►
April
(5)
►
March
(4)
►
February
(3)
►
January
(5)
▼
2010
(31)
►
December
(4)
►
November
(4)
▼
October
(5)
PR29-10-10. Progress Report from 23 to 29 Oct 2010
PR22-10-10. Progress Report from 16 to 22 Oct 2010
PR15-10-10. Progress Report from 9 to 15 Oct 2010
PR08-10-10. Progress Report from 2 to 8 Oct 2010
PR01-10-10. Progress Report from 25 Sept to 1 Oct ...
►
September
(4)
►
August
(4)
►
July
(6)
►
June
(4)
About Me
Leedon Heights Condo
View my complete profile