PR26-11-10. Progress Report from 20 to 26 Nov 2010
Preparation works for hoarding
Re-locate of water pipe
Preparation works for Landscaping
Steel structural for canopy
M&E dimantle works at affected show flat area
FCU & ducting dismantled
Material for new columns & beams
Hacking works to amended show flat layout
Preparation works for erection of new columns at Living /Dining
Roof area affected for new structural works
Construct of new columns & beams at Living/Dining area
Thursday, November 18, 2010
PR19-11-10. Progress Report from 13 to 19 Nov 2010
Granite feature wall
Alum. cladding at S/pool area
Works at Receiving Pavilion
Drainage works along Car-park
Main in-coming water pipe
Soil back-fill for landscape
Dismantle work of dry-walls & false ceilings to show-flat Amended location
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)
Followers
Blog Archive
►
2011
(43)
►
October
(4)
►
September
(5)
►
August
(4)
►
July
(4)
►
June
(5)
►
May
(4)
►
April
(5)
►
March
(4)
►
February
(3)
►
January
(5)
▼
2010
(31)
►
December
(4)
▼
November
(4)
PR26-11-10. Progress Report from 20 to 26 Nov 2010
PR19-11-10. Progress Report from 13 to 19 Nov 2010
PR12-11-10. Progress Report from 7 to 12 Nov 2010
PR06-11-10. Progress Report from 30 Oct to 6 Nov 2010
►
October
(5)
►
September
(4)
►
August
(4)
►
July
(6)
►
June
(4)
About Me
Leedon Heights Condo
View my complete profile