Thursday, September 29, 2011

PR30-9-11. Progress Report from 24 to 30 Sept 2011


revised s/s top & drawer for island counter


signage works beside media wall

skirting at dining

final paint works for revised fire escape door

revised model/model stand



replacement of plants at s/pool deck


installation of ID root works at Receiving pavilion & Sales gallery

landscape along retaining wall

Thursday, September 22, 2011

PR23-9-11. Progress Report from 17 to 23 Sept 2011


widening of fire escape door


revised works to wet-kitchen ceiling height


granite feature wall & landscape works along boundary/main entrance

delivery of dungeon root for main foyer

steel works progress (facing Leedon rd)

(facing Farrer rd)

final polishing of marble at revised dining

delivery of pendant light for dining

Thursday, September 15, 2011

PR16-9-11. Progress Report from 10 to 16 Sept 2011


frosted film for discussion room
dry laying of marble

marble wall in bath1 (after concealed of door opening)


marble flooring to expanded dining area

polishing of marble flooring


granite feature wall for main entrance & car-park area
casting for additional footings 

steel works for main signage (facing farrer rd)


steel works for feature-wall (facing leedon hts)

Thursday, September 8, 2011

PR9-9-11. Progress Report from 3 to 9 Sept 2011

completed dry wall/ceiling works (pending marble flr mat'l)

testing of media screen


granite for main entrance feature wall (car-park)


installaton works for granite feature wall


show-flat main signage steel works progress