Thursday, October 27, 2011

PR28-10-11. Progress Report from 22 to 28 Oct 2011



i.d works in bedroom


bracket for glass at both ends of covered-walkway

Thursday, October 20, 2011

PR21-10-11. Progress Report from 15 to 21 Oct 2011



installation of frosted film

installation of wardrobe in BR

landscape at front entrance

r.c ramp at walkway


steel works at main signage

Thursday, October 13, 2011

PR14-10-11. Progress Report from 8 to 14 Oct 2011


light for dining


A/c at guard-house

label for car-park lot

landscaping work at front entrance

Thursday, October 6, 2011

PR7-10-11. Progress Report from 1 to 7 Oct 2011



delivery of marble dining table


installation of shelving at Dining




cabinetry works at wet-kitchen/laundry

dismantling of shelve in 'Study'


revised landscaping at front car-park area


signage at main entrance