Thursday, May 19, 2011

PR20-5-11. Progress Report from 14 to 20 May 2011

Delivery of electrical appliances




Installation of appliances

Final coat/tint of timber flooring in BRs

Laying of timber decking at S/pool area

Installation of skirting

Wine shelve in Home-shelter
Sealing and painting to temp. access to show-unit


On-site spraying of alum. verticle trellis for Receiving Pavilion 





Installation of light fixtures
Temp. fix of basin for P.U.B inspection

Wednesday, May 18, 2011

PR13-5-11. Progress Report from 7 to 13 May 2011





Cabinetry works at dry-kitchen

Cabinetry at MBR/Mbath

Cabinetry at BR1 & 2


Cabinetry at Bath1 & 2
Cabinetry at Gallery


Installation of glass pane at LR/Dining area
Final epoxy coating at Galleries

Closing/ make good of temperary access to show-unit


Laying of carpet grass

Opening of door access at office

Thursday, May 5, 2011

PR6-5-11. Progress Report from 30 April to 6 May 2011

Installation of glass wall at BRs  





Carpentry works to show-unit 

Landscape along retaining wall

Painting works at external area
Defect rectificaton works to external wall cracks

Water seepage (peeling of paint) at Main foyer