Thursday, September 22, 2011

PR23-9-11. Progress Report from 17 to 23 Sept 2011


widening of fire escape door


revised works to wet-kitchen ceiling height


granite feature wall & landscape works along boundary/main entrance

delivery of dungeon root for main foyer

steel works progress (facing Leedon rd)

(facing Farrer rd)

final polishing of marble at revised dining

delivery of pendant light for dining

Thursday, September 15, 2011

PR16-9-11. Progress Report from 10 to 16 Sept 2011


frosted film for discussion room
dry laying of marble

marble wall in bath1 (after concealed of door opening)


marble flooring to expanded dining area

polishing of marble flooring


granite feature wall for main entrance & car-park area
casting for additional footings 

steel works for main signage (facing farrer rd)


steel works for feature-wall (facing leedon hts)

Thursday, September 8, 2011

PR9-9-11. Progress Report from 3 to 9 Sept 2011

completed dry wall/ceiling works (pending marble flr mat'l)

testing of media screen


granite for main entrance feature wall (car-park)


installaton works for granite feature wall


show-flat main signage steel works progress

Thursday, September 1, 2011

PR2-9-11. Progress Report from 27 Aug to 2 Sept 2011




Remover/dimantle works to show-unit



erection of new steel column


jointing of removed column
erection of new dry-wall
column removed






steel structural works in-progress at showflat main signage area

replacement of damage drain-cover