Thursday, December 2, 2010

PR3-12-10. Progress Report from 27 Nov to 3 Dec 2010


Feature wall progress at Receiving Pavilion


Skim coat for wall at S/pool area



Grating for drainage in progress







Structural works for propose hoarding







Erection of new column at Kitchen area

Thursday, November 25, 2010

PR26-11-10. Progress Report from 20 to 26 Nov 2010


Preparation works for hoarding


Re-locate of water pipe



Preparation works for Landscaping


Steel structural for canopy






M&E dimantle works at affected show flat area





FCU & ducting dismantled


Material for new columns & beams




Hacking works to amended show flat layout




Preparation works for erection of new columns at Living /Dining









Roof area affected for new structural works














Construct of new columns & beams at Living/Dining area