Thursday, May 5, 2011

PR6-5-11. Progress Report from 30 April to 6 May 2011

Installation of glass wall at BRs  





Carpentry works to show-unit 

Landscape along retaining wall

Painting works at external area
Defect rectificaton works to external wall cracks

Water seepage (peeling of paint) at Main foyer

Thursday, April 28, 2011

PR29-4-11. Progress Report from 23 to 29 April 2011

show-unit carpentry/ wall panels works 
Laying of timber strips in BRs
S/pool water ponding
Irrigation system for landscape
Glass panel at Gallery/ Entrance
Landscaping works along retaining wall
Laying of car-park interlocking pavers
Car park entrance wall feature works

Friday, April 22, 2011

PR22-4-11. Progress Report from 16 to 22 April 2011




Light fixtures at Powder room

Polishing/ Horning of marble flooring at Show-unit

Installation of alum.window frame at show-unit
Installation of floor granite at Main foyer
Works for main entrance



Preparation works for car-park

Interlocking floor for car-park

Thursday, April 14, 2011

PR15-4-11. Progress Report from 9 to 15 April 2011

Installation of marble wall/floor
Wall panel works
Screen wall
Exit sign & fire alarm
Landscaping works along 'side gate'
Closure & re-instate of railing at 'side gate'
Construction of drain along car park area
Construction of wall feature at Main Entrance