Thursday, January 27, 2011

PR28-1-11. Progress Report from 22 to 28 Jan 2011


Dry-walls


Media-wall


Painting works


C.U connection


Doors installed at Powder



Ceiling works at Canopy & Receiving Pavilion





Landscape




Trimming of trees





Construction of man-hole at 3rd shaft
Escavation works for connection of sewer pipe

Thursday, January 20, 2011

PR21-1-11. Progress Report from 15 to 21 Jan 2011




Erection of ceiling in progress





Water-proofing at wet area





Back-filling/level of soil for landscape




C.U connection in progress



Expansion of 3rd shaft (as position of pipe out by 2m from existing shaft)
Connection of Jack-in pipe at 3rd shaft

Thursday, January 13, 2011

PR14-1-11. Progress Report from 8 to 14 Jan 2011


Painting works at Sales Gallery



Party of dry-wall joint



Slide door for Powder corridor



Installation of alum. roof works at Receiving Pavilion




Construct & casting of drainage system


Jack-in pipe works at shaft no.2



Excavation of shaft no.3 for Jack-in pipe

Thursday, January 6, 2011

PR7-1-11. Progress Report from 2 to 7 Jan 2011


Installation of Aluminium Roof to canopy

Jeck-In pipe in progress


Drainage works along main show-flat area

Sunday, January 2, 2011

PR31-12-10. Progress Report from 26 to 31 Dec 2010

Application of silicon to glass panes




Erection of new dry-wall to amended layout




ACMV works



Carpentry works at Powder


Aluminium cladding works

Excavation of Shaft no.2 for Jack-in pipe