PR21-1-11. Progress Report from 15 to 21 Jan 2011




Erection of ceiling in progress





Water-proofing at wet area





Back-filling/level of soil for landscape




C.U connection in progress



Expansion of 3rd shaft (as position of pipe out by 2m from existing shaft)
Connection of Jack-in pipe at 3rd shaft