Thursday, February 24, 2011

PR25-2-11. Progress Report from 19 to 25 Feb 2011


Installation of cabinetry in office

Painting works


Steel structure for bay-window at Bedroom 2





Electrical works



Under-side of Roof at Covered-walkway

Preparation works for laying of Granite flooring




Hacking works for Main connection of sewer

Thursday, February 17, 2011

PR18-2-11. Progress Report from 12 to 18 Feb 2011

Painting works






Revised ACMV works at various location



Skylight at Bedroom 2




Curtain-wall /Skylight at S.pool area



Installation of Covered-walkway alum. roof (underside)





Completed Granite feature-wall


Installation of granite flooring at Receiving Pavilion


Re-inforced structure for I.D Art-work at Receiving Pavilion



Construction of I.C for showflat

Thursday, February 10, 2011

PR11-2-11. Progress Report from 29 to 31 Jan and 8 to 11 Feb 2011

Amended ceiling & cove at show-flat foyer


Opening for Frameless glass pane at Living


Alum. frameworks at Bedrooms


Ceiling painting works along Balcony









Installation of curtain wall & skylight at S/pool




Construction of drainage/paveway


Granite feature wall at Receiving Pavilion


Landscaping works