Amended ceiling & cove at show-flat foyer
Opening for Frameless glass pane at Living
Alum. frameworks at Bedrooms
Ceiling painting works along Balcony
Installation of curtain wall & skylight at S/pool
Construction of drainage/paveway
Granite feature wall at Receiving Pavilion
Landscaping works
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
Followers
Blog Archive
▼
2011
(43)
►
October
(4)
►
September
(5)
►
August
(4)
►
July
(4)
►
June
(5)
►
May
(4)
►
April
(5)
►
March
(4)
▼
February
(3)
PR25-2-11. Progress Report from 19 to 25 Feb 2011
PR18-2-11. Progress Report from 12 to 18 Feb 2011
PR11-2-11. Progress Report from 29 to 31 Jan and 8...
►
January
(5)
►
2010
(31)
►
December
(4)
►
November
(4)
►
October
(5)
►
September
(4)
►
August
(4)
►
July
(6)
►
June
(4)
About Me
Leedon Heights Condo
View my complete profile
No comments:
Post a Comment