PR26-8-11. Progress Report from 20 to 26 Aug 2011
Protection works to show-unit for alteration works
dismantle of dry-walls & others works affected
remote blind at sales gallery
footings for features wall at main signage
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
Followers
Blog Archive
▼
2011
(43)
►
October
(4)
►
September
(5)
▼
August
(4)
PR26-8-11. Progress Report from 20 to 26 Aug 2011
PR19-8-11. Progress Report from 13 to 19 Aug 2011
PR12-8-11. Progress Report from 6 to 12 Aug 2011
PR5-8-11. Progress Report from 30 July to 5 Aug 2011
►
July
(4)
►
June
(5)
►
May
(4)
►
April
(5)
►
March
(4)
►
February
(3)
►
January
(5)
►
2010
(31)
►
December
(4)
►
November
(4)
►
October
(5)
►
September
(4)
►
August
(4)
►
July
(6)
►
June
(4)
About Me
Leedon Heights Condo
View my complete profile
No comments:
Post a Comment