Thursday, June 9, 2011

PR10-6-11. Progress Report from 4 to 10 June 2011



installation of skirting to BRs

dis-mantling of cabinet &island at wet kitchen

installation of veneer to powder room




installation of marble to island/reception counter
alteration of model stand

landscaping works


gravers along car-park area


installation of granite feature wall at main car-park entranceconstruction of main gate base track

Thursday, June 2, 2011

PR3-6-11. Progress Report from 28 May to 3 June 2011

cabinetry for office
doors to landscape
window at masterbathroom

timber-deck at S/pool
stone pebbles along S/pool

gravers along covered-linkway
light fixtures along covered link-way
landscaping works at linkway

light fixtures & granite flooring at receiving pavilion

ceiling works at receiving pavilion

timber bench at receiving pavilion


works at main car-park entrance feature wall
model stand

Thursday, May 26, 2011

PR27-5-11. Progress Report from 21 to 27 May 2011


Grating for S/pool

Laying of pebbles over S/pool grating

Laying of loose pavers along covered linkway
Carpentry works for office






Insallation of light fixtures

Alum. works



Re-locate/alteration of fcu

Speaker for sound system


Installation of trellis at Receving pavilion