PR10-6-11. Progress Report from 4 to 10 June 2011
installation of skirting to BRs
dis-mantling of cabinet &island at wet kitchen
installation of veneer to powder room
installation of marble to island/reception counter
alteration of model stand
landscaping works
gravers along car-park area
installation of granite feature wall at main car-park entrance
construction of main gate base track
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
Followers
Blog Archive
▼
2011
(43)
►
October
(4)
►
September
(5)
►
August
(4)
►
July
(4)
▼
June
(5)
PR1-7-11. Progress Report from 26 June to 1 July 2011
PR24-6-11. Progress Report from 18 to 24 June 2011
PR17-6-11. Progress Report from 11 to 17 June 2011
PR10-6-11. Progress Report from 4 to 10 June 2011
PR3-6-11. Progress Report from 28 May to 3 June 2011
►
May
(4)
►
April
(5)
►
March
(4)
►
February
(3)
►
January
(5)
►
2010
(31)
►
December
(4)
►
November
(4)
►
October
(5)
►
September
(4)
►
August
(4)
►
July
(6)
►
June
(4)
About Me
Leedon Heights Condo
View my complete profile
No comments:
Post a Comment