Thursday, September 15, 2011

PR16-9-11. Progress Report from 10 to 16 Sept 2011


frosted film for discussion room
dry laying of marble

marble wall in bath1 (after concealed of door opening)


marble flooring to expanded dining area

polishing of marble flooring


granite feature wall for main entrance & car-park area
casting for additional footings 

steel works for main signage (facing farrer rd)


steel works for feature-wall (facing leedon hts)

Thursday, September 8, 2011

PR9-9-11. Progress Report from 3 to 9 Sept 2011

completed dry wall/ceiling works (pending marble flr mat'l)

testing of media screen


granite for main entrance feature wall (car-park)


installaton works for granite feature wall


show-flat main signage steel works progress

Thursday, September 1, 2011

PR2-9-11. Progress Report from 27 Aug to 2 Sept 2011




Remover/dimantle works to show-unit



erection of new steel column


jointing of removed column
erection of new dry-wall
column removed






steel structural works in-progress at showflat main signage area

replacement of damage drain-cover

Thursday, August 25, 2011

PR26-8-11. Progress Report from 20 to 26 Aug 2011









Protection works to show-unit for alteration works

dismantle of dry-walls & others works affected

remote blind at sales gallery

footings for features wall at main signage