Thursday, December 23, 2010

PR24-12-10. Progress Report from 18 to 24 Dec 2010


Installation of glass panes at Main Gallery


Aluminium works at S/pool area


Water proofing at S/pool water feature & Bath 2




Shaft for Jack-in pipes

Thursday, December 16, 2010

PR17-12-10. Progress Report from 11 to 17 Dec 2010


Feature wall at receiving pavilion (pending mat'l)



Planting of cow grass behind showflat office



Planting of bamboos along Covered-walkway




Installation works of door frame at Powder



Dismantled cabinetries from amended Showflat office



Soil excavation for Jack-in pipe





Monitoring system for Jack-in pipe


Dismantled column at Liv/Din area







New columns location at MBR & study



New column location at Dry kitchen/Garden 2



New column location at Foyer area




New column location at Laundry/Wet kitchen

Thursday, December 9, 2010

PR10-12-10. Progress Report from 4 to 10 Dec 2010





Feature Wall at Receiving Pavilion




Sealant applcation to granite stone



Erection of new dry-wall to amended layout



Installation of glass at front Gallery


Erection of wall for water feature at S/pool area





Delivery of partial plants for landscape



Preparation works for landscape






Setting out monitoring system for Jack-in pipe








Erection of Hoarding works