PR17-12-10. Progress Report from 11 to 17 Dec 2010


Feature wall at receiving pavilion (pending mat'l)



Planting of cow grass behind showflat office



Planting of bamboos along Covered-walkway




Installation works of door frame at Powder



Dismantled cabinetries from amended Showflat office



Soil excavation for Jack-in pipe





Monitoring system for Jack-in pipe


Dismantled column at Liv/Din area







New columns location at MBR & study



New column location at Dry kitchen/Garden 2



New column location at Foyer area




New column location at Laundry/Wet kitchen