PR10-12-10. Progress Report from 4 to 10 Dec 2010





Feature Wall at Receiving Pavilion




Sealant applcation to granite stone



Erection of new dry-wall to amended layout



Installation of glass at front Gallery


Erection of wall for water feature at S/pool area





Delivery of partial plants for landscape



Preparation works for landscape






Setting out monitoring system for Jack-in pipe








Erection of Hoarding works