PR25-3-11. Progress Report from 19 to 25 Mar 2011
I.D wall feature works at show-unit
Erection of screen-wall at reception area
Revised ACMV return at Gallery
Light fixtures for office
Glass-panel wall above canopy
Completed roofing works for Covered-walkway
Landscape works in progress
Laying of lean concrete at retaining wall area
Re-bar for retaining wall
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
Followers
Blog Archive
▼
2011
(43)
►
October
(4)
►
September
(5)
►
August
(4)
►
July
(4)
►
June
(5)
►
May
(4)
►
April
(5)
▼
March
(4)
PR25-3-11. Progress Report from 19 to 25 Mar 2011
PR18-3-11. Progress Report from 12 to 18 Mar 2011
PR11-3-11. Progress Report from 5 to 11 Mar 2011
PR4-3-11. Progress Report from 26Feb to 4 Mar 2011
►
February
(3)
►
January
(5)
►
2010
(31)
►
December
(4)
►
November
(4)
►
October
(5)
►
September
(4)
►
August
(4)
►
July
(6)
►
June
(4)
About Me
Leedon Heights Condo
View my complete profile
No comments:
Post a Comment