PR1-4-11. Progress Report from 26 Mar to 1 April 2011
Rectification works for external wall
Installation of electric socket
Erection of screen wall
Hacking/removing of marble flooring at Foyer & Dry-kitchen
Laying of floor tiles at Wet-kitchen
Compaction of soil for landscaping
Back-fill of soil along retaining wall
Retaining wall (1st tier)
Retaining wall (2nd tier)