Thursday, June 30, 2011

PR1-7-11. Progress Report from 26 June to 1 July 2011


installation of wall-paper




revised light-fixtures in various location

installation of handle/lockset at powder



landscaping works along car-park/front entrance

Sunday, June 26, 2011

PR24-6-11. Progress Report from 18 to 24 June 2011


sanitary fittings in powder rooms



glass panes wall

shower screen glass



glass panes along Bedrooms
BRC boundary fence
landscape at fencing

granite feature wall works

installation of main gate

Thursday, June 16, 2011

PR17-6-11. Progress Report from 11 to 17 June 2011


Revised cabinetry works in dry-kitchen

Installation of door jam/frame at Mbr, Study & Br1
Revised wall panel works in powder-rooms
book-selving in study
installation of switches

wall paper in Br2


granite planter box & water feature at S/pool
installation of fire escape door
lighting at galleries 

revised model stand


cabinetries at pantry & show-kitchen

installation of BRC fencing 
Main car-park entrance granite feature wall


installation of main car-park entrance gate frame