Thursday, June 16, 2011

PR17-6-11. Progress Report from 11 to 17 June 2011


Revised cabinetry works in dry-kitchen

Installation of door jam/frame at Mbr, Study & Br1
Revised wall panel works in powder-rooms
book-selving in study
installation of switches

wall paper in Br2


granite planter box & water feature at S/pool
installation of fire escape door
lighting at galleries 

revised model stand


cabinetries at pantry & show-kitchen

installation of BRC fencing 
Main car-park entrance granite feature wall


installation of main car-park entrance gate frame