Thursday, July 28, 2011

PR29-7-11. Progress Report from 23 to 29 July 2011






installation of mirrors & fixtures in Baths


timber trim at edge between reflective pool & carpet
revised cove at sales gallery

hood in wet kitchen


remover of defective trees 6nos. 

wallpaper in MBR

Friday, July 22, 2011

PR22-7-11. Progress Report from 16 to 22 July 2011



Installation of Main door at show-flat foyer

glass works at discussion room



s/s works at show-kitchen cabinet

revised cove/cove light at sales gallery




sanitary fittings for all baths

carpentry works in MBr & Br2
s/s backing at wet-kitchen cabinet


carpentry works in office

revised wardrobe at MBr
landscaping works

ramp at main car-park entrance


setting up for photo shoot in Lv/din & Br1

Thursday, July 14, 2011

PR15-7-11. Progress Report from 9 to 15 July 2011

Mbath cabinetry works




Solid surface top (except Bath2 & Powder)
pivot door at powder

cabinetry at powder

cabinetry in office area
final floor screed in office


blinds along sales gallery

s/s divider strip for carpet



laying of carpet

installation of glass at dicussion rm


light at show-kitchen
main foyer door


erection of guard-house


loose furnitures