Friday, July 22, 2011

PR22-7-11. Progress Report from 16 to 22 July 2011



Installation of Main door at show-flat foyer

glass works at discussion room



s/s works at show-kitchen cabinet

revised cove/cove light at sales gallery




sanitary fittings for all baths

carpentry works in MBr & Br2
s/s backing at wet-kitchen cabinet


carpentry works in office

revised wardrobe at MBr
landscaping works

ramp at main car-park entrance


setting up for photo shoot in Lv/din & Br1