PR8-7-11. Progress Report from 2 to 8 July 2011


installation of track for curtain
installation of sanitary fittings

removing of floor protection & cleaning

revised lighting for landscapingcarpentry works in office


erection of guard-house


installation of automated system for main gate
removing of granite feature wall along retaining wall (due to some lippage defect of tile)