Thursday, December 16, 2010
PR17-12-10. Progress Report from 11 to 17 Dec 2010
Feature wall at receiving pavilion (pending mat'l)
Planting of cow grass behind showflat office
Planting of bamboos along Covered-walkway
Installation works of door frame at Powder
Dismantled cabinetries from amended Showflat office
Soil excavation for Jack-in pipe
Monitoring system for Jack-in pipe
Dismantled column at Liv/Din area
New columns location at MBR & study
New column location at Dry kitchen/Garden 2
New column location at Foyer area
New column location at Laundry/Wet kitchen
Thursday, December 9, 2010
PR10-12-10. Progress Report from 4 to 10 Dec 2010
Feature Wall at Receiving Pavilion
Sealant applcation to granite stone
Erection of new dry-wall to amended layout
Installation of glass at front Gallery
Erection of wall for water feature at S/pool area
Delivery of partial plants for landscape
Preparation works for landscape
Setting out monitoring system for Jack-in pipe
Erection of Hoarding works
Thursday, December 2, 2010
PR3-12-10. Progress Report from 27 Nov to 3 Dec 2010
Feature wall progress at Receiving Pavilion
Skim coat for wall at S/pool area
Grating for drainage in progress
Structural works for propose hoarding
Erection of new column at Kitchen area
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)
Followers
Blog Archive
▼
2011
(43)
▼
October
(4)
PR28-10-11. Progress Report from 22 to 28 Oct 2011
PR21-10-11. Progress Report from 15 to 21 Oct 2011
PR14-10-11. Progress Report from 8 to 14 Oct 2011
PR7-10-11. Progress Report from 1 to 7 Oct 2011
►
September
(5)
►
August
(4)
►
July
(4)
►
June
(5)
►
May
(4)
►
April
(5)
►
March
(4)
►
February
(3)
►
January
(5)
►
2010
(31)
►
December
(4)
►
November
(4)
►
October
(5)
►
September
(4)
►
August
(4)
►
July
(6)
►
June
(4)
About Me
Leedon Heights Condo
View my complete profile