Friday, April 1, 2011

PR1-4-11. Progress Report from 26 Mar to 1 April 2011


















Rectification works for external wall


































Installation of electric socket





























Erection of screen wall


































Hacking/removing of marble flooring at Foyer & Dry-kitchen





































Laying of floor tiles at Wet-kitchen














Compaction of soil for landscaping



























Back-fill of soil along retaining wall

































































Retaining wall (1st tier)


































Retaining wall (2nd tier)

Thursday, March 24, 2011

PR25-3-11. Progress Report from 19 to 25 Mar 2011


I.D wall feature works at show-unit

Erection of screen-wall at reception area


Revised ACMV return at Gallery




Light fixtures for office




Glass-panel wall above canopy



Completed roofing works for Covered-walkway








Landscape works in progress




Laying of lean concrete at retaining wall area


Re-bar for retaining wall

Thursday, March 17, 2011

PR18-3-11. Progress Report from 12 to 18 Mar 2011


Light fixture works in progress


Installation of alum. pitch roof at Covered-walkway



Works for feature walls in Show-unit




Laying of marble flooring in Show-unit



Re-inforced structure for I.D works



Roof works above Canopy



Drainage at carpark area